Penarth Dock, South Wales - 150 years - the heritage and legacy  
Penarth Dock, South Wales - the heritage & legacy . . .

about . . .

Volume Ten - Pre-Victorian to the present day - even more aspects - Penarth Harbour, Dock & Railway Company . . .

Fencing
Ballast
Timber (creosoted)
Timber (uncreosoted)
Laying perm't. way

2/-
1/9
3/2½
2/9½
1/-
per lin. yard
per cubic yard
per foot
per foot
per yard

3.10.1858 : Resolved, that the Engineers be desired to prepare and lay plans of the Dock before the Committee of Works, as preparatory to advertising for tenders.

Payment, Messrs. Rennie & Co. - (Cert. No. 9) - £13,656 - 18 - 8d

8.12.1858 : At a meeting at Mr. Hawkshaw's office, London, held 11th November 1858, Mr. Dobson submitted a plan of the public wharf approaches, which was approved, and instructions given to let the work to Messrs. Rennie & Coy. at the same prices as the Coal Drops. Mr. Dobson to prepare a contract accordingly.

Resolved, that the said approval and instructions be and are confirmed.

15.12.1858 : Contract for the Public Wharf with Messrs. Rennie & Coy. sealed.

Ordered, that the Committee of Works report to the next meeting of the Board on the general arrangements necessary for the opening of the undertaking.

Mr. Dobson stated that he had called upon the Contractors to remove the Slip in the second reach of the river, believing it to be in accordance with the terms of the Contract for them to do so. They had, however, declined, and the Slip was, therefore, still in the river, causing serious injury to the rest of the slopes.

Ordered, that the Engineers be desired to give their immediate attention to this matter. The Director's clearly understand that they are in no way liable to remove the Slip at the Company's expense.

Home
About
Contact

contents . . .
Introduction
Contents

information . . .
Search this site
Contributions
Links
Recent Updates

150 years of Penarth Dock History and Heritage

© 2014 - 2025 - penarth-dock.org.uk - all rights reserved - web design by Dai the Rat